Denmead Poultry Farm

Completed in four separate site visits, this project included the erection and later dismantling of extensive scaffolding for construction work.

  • Visit 1: Full perimeter scaffold (approx. 60m) at one lift high, including a 4m loading bay and full internal birdcage scaffold
  • Visit 2: Scaffold raised to a second lift level for brickwork
  • Visit 3: Gable end scaffolding added with hop-ups on both ends for roofing and brickwork completion
  • Visit 4: Full dismantling and site clearance

This phased approach ensured efficient progress and minimal disruption throughout the build.